    You have a project with the following activities. Activity 1 can start immediately and has a estimated duration of four. Activity 2 can start after activity 1 is completed and has an estimated duration of eight. Activity 3 can start after activity 2 is completed and has a duration of five. Activity 4 can start after activity 1 is completed and has an estimated duration of eight. Activity 5 has an estimated duration of three and must takes place concurrently with the activity 3.It can start after activities 4 and 2. What is the duration of critical path of this project?

    A 15
    B 18
    C 17
    D 12

    #2196
    admin
    Keymaster

    The correct answer is C.

    Path 1 – Start 1, 2, 3, End
    Path 2 – Start, 1, 2, 5, End
    Path 3 – Start 1, 4, 5, End

    Path 1 would take 4 + 8 + 5 days or 17 days to complete.
    Path 2 would take 4 + 8 + 3 days or 15 days to complete.
    Path 3 would take 4 + 8 + 3 days or 15 days to complete.
    Therefore, Path 1 is critical path

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.