A project has experienced significant delays due to equipment problems, staff attrition and slow client reviews. The project is 40% complete and has used 60% of available calendar time. What is the FIRST thing you should do?
a) Re-align the schedule to reflect the new date
b) Analyze the critical path activities for potential to fast track or crash the schedule
c) Document the lack of progress and associated issues to the management
d) Identify the activities required more time than planned