The product management for the product the project is developing notifies the project manager that she has decided the product should be usable by the additional market. The BEST thing for the project manager to do would be to?
a) Immediately notify the project sponsor that there is a project scope change
b) Notify the project change control board that the project scope will have to change.
c) Inform the product manager that the potential impacts to the project will be reviewed.
d) Do nothing, as this is an example of progressive evaluation