The correct answer is D.
Choice A is inappropriate, since it is the functional manager’s responsibility. Choice B is not problem solving, it is more like avoidance or withdrawal, something that is not usually best. Choice C is a penalty, as it is discussed at a team meeting. By saying that “this person has participated in?”, the question is saying that you as the project manager have done everything in your power already. There is even a reward system in place. Therefore, it is time to ask for help from management. Functional management is responsible for addressing individual performance problems.