    A project manager has just been assigned to a project that has been in progress for 2 months when a team member requests more time on an activity he is working on. The project manager discovers that the only impact to the project will be a delay on the non critical path activity. The customer has emphasized the importance of completing the project on schedule. What should the project manager do NEXT?

    a) Submit the information to the change control board, determine if the event might impact the team member’s future work, inform the team member of the board’s decision.
    b) Ask the team member why they need more time, begin integrated change control, adjust the project schedule as needed.
    c) Look for impacts to quality, cut unneeded scope from the project, ask for more resources.
    d) See if any stakeholder objects to the change. Calculate the exact impact on the project, look at removing this resource from the project.

    #2005
    admin
    Keymaster

    The correct answer is A.

    The use of the phrase “only impact” here implies integrated change control has already been done, thus eliminating choices B and C. Did you select choice B because you liked the idea of asking the team member why? Realize that would have been done before you determined the ONLY impact. The change control board members are the selected representatives of the stakeholders, so choice D cannot be the best choice. Once reviewed, the board formally rejects or approves changes.

    Revise Integration Management Concepts – Integration Management Course

    Quiz:

    20-Questions Challenge

    50-Questions Challenge

     

     

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.