During the implementation of a contingency plan , a team member notices that the plan worked only marginally. There were 3 similar contingency plans developed for other risks that have not yet happened. He should recommend which of the following?
a) A workaround
b) A project change request
c) A new risk rating matrix
d) A risk responsibility chart review