    During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had assess to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by the stakeholders. The BEST thing for the project manager to do is to?
    a) Let the sponsor know of the stakeholder request.
    b) Evaluate the impact of adding the scope
    c) Tell the stakeholders the scope cannot be added
    d) Add the work if there is time available in the project schedule.

    #1991
    admin
    Keymaster

    The correct answer is C.

    Based on the information presented, there is no reason to try to convince the sponsor to add the work (choices B and D). Though one could let the sponsor know (choice A) the best choice would be to say no. A better choice would be to find the root cause of the problem, but that choice is not listed here.