The project manager has had some difficulty in getting the team to complete work efforts but he feels that the changes he made to the reward system will fix the problem. The no. of stakeholders on the project has grown by 20% and the no. of activities being completed late is growing. The project manager has heard from management that project might become a high priority if their competition comes out with a new product that uses wireless technology. Based on this, it would be best for the project manager to?
a) Re-estimate the activities and prepare to create a new schedule.
b) Perform configuration management
c) Recreate the project work authorization system
d) Better respond to risk event triggers