    The customer requests a change to the project that might increase the project risk. Which of the following should you do before all the others?

    a) Include the expected monetary value of the risk in the new cost estimate.
    b) Talk to the customer about the impact of change
    c) Analyze the impacts of the change with the team
    d) Change the risk management plan.

    #5436
    admin
    Keymaster

    Correct answer is c.

    Impact of changes need to be evaluated before anything else.