    Stakeholder analysis is a technique of systematically gathering and analyzing quantitative and qualitative
    information to determine whose interests should be taken into account throughout the project. It is important to prioritize the stakeholders to ensure the efficient use of the effort to communicate and manage their expectations. Which of the classification model is not used in stakeholder analysis?
    A. Salience/influence grid
    B. Power/influence grid
    C. Power/interest grid
    D. Salience model

    #1773
    Gary
    Guest

    Correct Answer is A.

    There are 4 classification models:
     Power/interest grid- grouping the stakeholders on power and interest
     Power/influence grid- grouping stakeholders on power and influence (active involvement)
     Influence/impact grid- grouping stakeholder on influence (active involvement) and impact (ability to effect changes to project’s planning or execution)
     Salience model- grouping stakeholders based on their power, urgency, and legitimacy.
    Power= ability to impose will. Urgency= need for immediate action. Legitimacy = their
    involvement is appropriate.