    During the identify risk process, a project manager made a long list of risks identified by all the stakeholders using various methods. He then made sure that all risks were understood and all triggers had been identified. Later, in the plan risk response process, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong?

    a) The project manager should have waited until the Perform Qualitative risk analysis process to get the stakeholders involved.
    b) More people should be involved in the plan risk response process
    c) The project manager should have created workarounds
    d) Triggers are not identified until the Identify Risks process.

    #1731
    admin
    Keymaster

    The correct answer is B.

    Risk response owners and other stakeholders should be included in the plan risk responses.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.