    During a project, two stakeholders disagree on the acceptance criteria for one outcome. What should a project manager do?

    1. Check the base level of the area
    2. Hold a meeting with stakeholders
    3. Review the requirements documentation
    4. Update the risk register and risk response plan

    #13451
    Gaurav
    Guest

    Answer 3. Review the requirements documentation

    It helps to know what the exact expectation is and what would be the acceptance criteria for the requirements.