    An Agile team is conducting retrospective session. They are deciding what can be done in the upcoming sprints to improve their performance. All of the followings can be useful to them except:

    a. Short Subjects
    b. Smart Goals
    c. Circle of Questions
    d. Plus/Delta

    #12596
    admin
    Keymaster

    Correct answer is D.

    Since the team is deciding what to do in the upcoming sprint, therefore, they are in the “Decide what to do” phase. Plus/Delta is being used in the Close Retrospective phase. All others are used in the “Decide what to do” phase.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.