    During the upcoming release planning, Epics were decomposed into smaller stories and the summation of story points of smaller stories got decreased as compared to that of epic. What effect this will have on the Burndown chart?

    a. There will be no change
    b. Burndown graph will go up
    c. Burndown graph will go down
    d. Nothing can be concluded from this information

    #11944
    admin
    Keymaster

    Correct answer is C.

    Since the total number of story points got decreased after decomposing epic into smaller stories so burndown graph will go down.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master Scrum Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    All Scrum Question & AnswersQuestion & Answers

    Revise Scrum ConceptsScrum Concepts

    Scrum UpdatesScrum Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.