    An agile team was performing very well till the fourth iteration. However, due to some unforeseen situations, it was not able to complete any story in the fifth iteration. How this situation will effect the burndown chart?

    a. Slope of the burndown chart will become negative
    b. Slope of the burndown chart will become zero
    c. Slope of the burndown chart will become positive
    d. Since the situation was unforeseen so fifth iteration would be cancelled

    #11900
    admin
    Keymaster

    Correct answer is B.

    Since zero story points are completed so the line in the burndown graph would become flat. Thus slope would become zero.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master Scrum Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    All Scrum Question & AnswersQuestion & Answers

    Revise Scrum ConceptsScrum Concepts

    Scrum UpdatesScrum Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.