    Team A is averaging 50 storypoints per three weeks sprint. 200 points worth of functionality is left. How many more weeks would be required to complete the remaining work?

    A. 0.25
    B. 3
    C. 4
    D. 12

    #11857
    admin
    Keymaster

    Correct answer is D.

    Number of sprints required = 200 / 50 = 4
    Number of weeks required = number of sprints * sprints duration = 4*3 = 12