Home Forums PMP Questions and Answers Discussion PMP Question 424

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #11738
    admin
    Keymaster

    Organization A has newly adopted Scrum methodology to execute the new project. Development team is facing issue coming from other team which is preventing them to go ahead in their project. Who is primarily responsible for resolving the issue?

    a) Scrum Master
    b) Product Owner
    c) Development Team
    d) Project Sponsor

    #11740
    admin
    Keymaster

    Correct answer is a.

    Scrum Master is primarily responsible to remove impediments from the team’s progress.

    Tips/Tricks/Cheatsheet to master PMP Exam and Concepts : Youtube Channel

    PMP/Agile Useful Resources : PMP/Agile Resources

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.